St. George Street Reconstruction
Project Description
In 2024, the County of Elgin in partnership with the Municipality of Central Elgin is planning to reconstruct St. George Street (County Road 26) to an urban road standard from Wellington Road (County Road 25) to the CN railway crossing. The reconstruction project will include the replacement of aging storm water infrastructure, road base reconstruction complete with sidewalk and curb installation, and asphalt placement.
Construction Detour
A tailored construction detour for each phase will be in place throughout the duration of the project. During construction, sections of the roads will need to be closed to vehicular through traffic to complete the work safely, and in a timely manner, however, pedestrian access will be provided to the extent possible.
- Paving is planned for the week of June 16, depending on the weather.
- Residents will receive a notice (via door hanger) the day before paving is confirmed.
- On paving day, driveways will be temporarily inaccessible for about 4 hours. If you need to leave during that time, please park on a nearby side street.
- Remove temporary asphalt curbs at catchbasins and raise catchbasins to finished grade
- Finish sidewalk installation including tactile plates
- Raise maintenance holes to finished grade
- Street sweep and prepare roadway for tack coat
- Complete surface asphalt and permanent pavement markings
Project Description
In 2024, the County of Elgin in partnership with the Municipality of Central Elgin is planning to reconstruct St. George Street (County Road 26) to an urban road standard from Wellington Road (County Road 25) to the CN railway crossing. The reconstruction project will include the replacement of aging storm water infrastructure, road base reconstruction complete with sidewalk and curb installation, and asphalt placement.
Construction Detour
A tailored construction detour for each phase will be in place throughout the duration of the project. During construction, sections of the roads will need to be closed to vehicular through traffic to complete the work safely, and in a timely manner, however, pedestrian access will be provided to the extent possible.
- Paving is planned for the week of June 16, depending on the weather.
- Residents will receive a notice (via door hanger) the day before paving is confirmed.
- On paving day, driveways will be temporarily inaccessible for about 4 hours. If you need to leave during that time, please park on a nearby side street.
- Remove temporary asphalt curbs at catchbasins and raise catchbasins to finished grade
- Finish sidewalk installation including tactile plates
- Raise maintenance holes to finished grade
- Street sweep and prepare roadway for tack coat
- Complete surface asphalt and permanent pavement markings
-
Contract Awarded for St. George Street Reconstruction Project
Share Contract Awarded for St. George Street Reconstruction Project on Facebook Share Contract Awarded for St. George Street Reconstruction Project on Twitter Share Contract Awarded for St. George Street Reconstruction Project on Linkedin Email Contract Awarded for St. George Street Reconstruction Project linkFollowing careful consideration of tender submissions, Elgin County Council has awarded PV-EX Construction Ltd. the contract for the St. George Street (CR 26) Reconstruction project. With a total price of $3,279,205, the bid comes in under budget, allowing for the timely commencement of construction. This vital infrastructure initiative, part of the 2024 Capital Budget, aims to enhance transportation links in the Municipality of Central Elgin, covering a stretch of 1.1 kilometres from Wellington Road (CR 25) to the Canadian National Railway (CN) spur line. Construction is expected to begin in mid-June 2024, with substantial completion anticipated by the end of October 2024. Final asphalt paving and minor restoration will be completed in 2025.
Elgin County would also like to recognize the Government of Ontario for its funding assistance with the St. George Street Reconstruction project through the Ontario Community Infrastructure Fund (OCIF). The Government of Ontario continues to strengthen communities through investments in the construction and repair of critical infrastructure, for which the County of Elgin is grateful to be a recipient. Elgin County received $2,650,000 as part of the OCIF program and has allocated 2024 funding to the St. George Street Reconstruction.
Follow Project
Documents
-
St. George Street Reconstruction - Notice of Curb Placement - August 21 2024 (320 KB) (pdf)
-
St. George Street Reconstruction - Notice of Construction - May 29, 2024 (286 KB) (pdf)
-
Updated Notice of Project - March 7, 2024 (770 KB) (pdf)
-
St. George Street Reconstruction Presentation - March 2024 (1.63 MB) (pdf)
-
Notice of Project FINAL - February 18, 2021 (368 KB) (pdf)
-
Preconstruction Survey FINAL - February 18, 2021 (200 KB) (pdf)
Construction Schedule
-
February 2021 – June 2021
St. George Street Reconstruction has finished this stagePre-Construction Investigations
-
Fall 2021
St. George Street Reconstruction has finished this stagePre-Construction Public Information Centre
-
Spring 2024*
St. George Street Reconstruction has finished this stageDesign Finalization
-
Summer 2024*
St. George Street Reconstruction has finished this stageConstruction Start
-
Fall 2024*
St. George Street Reconstruction has finished this stageEstimated completion by end of October 2024. Some minor cleanup work will be completed in the Spring of 2025.
-
June 2025
St. George Street Reconstruction is currently at this stageSurface asphalt paving, maintenance hole, and catchbasin final adjustments and outstanding deficiencies.
* Please note that the timelines are approximate and will vary depending on weather and other factors.