Terrace Lodge Redevelopment Construction Progress Update - Feb 8, 2022

Phase One of the project is progressing in accordance with the approved construction schedule and at this time is on track to move to Phase two in late 2022. Minor delays experienced to date have been a result of weather, a discrepancy in building dimensions and the time required to ensure the accuracy of the dimensions to proceed with construction. A summary of construction progress date is as follows:


  • March 2021 – Start of project, clearing of site and setting up of construction trailers and staging/storage areas. Construction of temporary access lane for the project.
  • April – May 2021 – Begin excavation of addition, prepare for the relocation of the existing ground mounted air handling units for north and south wings.
  • June – Aug 2021 - Continue to form and pour concrete foots, pads, and walls. Delays experienced do to multiple heavy rain events throughout the summer.
  • Sept – Nov 2021– Completion of foundation, installation of all underground electrical conduit and plumbing. The installation of all structural steel framing and metal studding. Ongoing installation of above ground electrical conduit, Mechanical rough in. Installation of concrete floor on ground level.
  • Dec – Jan 2022 – Completion of interior steel partitions, continued installation of mechanical, plumbing and electrical infrastructure throughout the addition. Installation of roofing material and placement of roof top HVAC equipment.

Share Terrace Lodge Redevelopment Construction Progress Update - Feb 8, 2022 on Facebook Share Terrace Lodge Redevelopment Construction Progress Update - Feb 8, 2022 on Twitter Share Terrace Lodge Redevelopment Construction Progress Update - Feb 8, 2022 on Linkedin Email Terrace Lodge Redevelopment Construction Progress Update - Feb 8, 2022 link