November 18, 2026 - Update
Thank you for your continued patience as we work towards completing the next phase of the Village of Fingal Reconstruction project. Below is an update regarding the upcoming work on Union Road, including some asphalt paving scheduled for the end of this week.
Upcoming Work
Crews are scheduled to begin lift of binder asphalt (base layer paving) work on Union Road on Friday, November 20, 2026, between the hours of 7 am and 5 pm, weather permitting.
The limits of the paving work will be on Union Road from the north side of the new entrance/exit to the sanitary pumping station site to the north limit of the existing roadwork.
It is important to note that this is not the final layer of asphalt. This initial layer, known as base or binder asphalt, provides a strong foundation that can handle heavy traffic and temperature changes. The final layer of asphalt, along with the construction of the new concrete sidewalk, finishing touches on the boulevard, and the paving of residential driveways, will be completed next year.
Access Impacts
Union Road remains closed to all traffic within the construction area.
Residents directly impacted by the asphalt paving operations are kindly asked to park their vehicle outside of the paving limits noted above on November 20th. Access to driveways will be temporarily unavailable during the paving work on Union Road.
Residents are asked to follow posted signage and use the signed detour during the closure.
Detour Route
Please follow the signed detour posted on Municipal Road 511:http://bit.ly/49eqvMc
Thank you for your continued patience and cooperation as this important infrastructure work progresses.
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends