January 9, 2026 - Update
We understand there were questions following this week's construction update in the Village of Fingal. The information below provides further clarification and details to help residents plan ahead.
Union Road Closure: January 12th
On Monday, January 12th, residents should expect a full closure of a portion of Union Road as the contractor completes work exiting the sanitary pump station with deep sewer installations. Due to the depth of the excavation, the roadway cannot be safely maintained for one lane of traffic and will be closed to all traffic.
- Closure limits: From Lanark Street to north of the pump station
- Detours: Please follow the official detours posted on Municipal Road 511. http://bit.ly/49eqvMc
- Map: See the map below for full closure details

Parking and Access
When sanitary installation in front of your property is taking place vehicular access will be blocked. The Consultant will notify residents beforehand where to park when access isn't permitted. The Contractor will be responsible for maintaining pedestrian access to all properties.
School Transportation
Starting on January 12th, the school bus company will resume pick up points at centralized locations. A temporary bus stop has been set up at the corner of Fingal Line and Union Rd.
Thank you for your patience as this work continues.