January 6, 2026 - Update
Village of Fingal Reconstruction Update
Bre-Ex Construction is back on site today, January 6, to continue reconstruction work in the Village of Fingal. Over the next two weeks, residents may notice activity related to the roadways, underground servicing, and pump station work.
Roadway and Underground Work
Crews will be preparing roads and underground services to support future construction. This includes:
- Locating existing underground utilities and completing test holes
- Removing road surfaces in parts of Stage 1
- Grinding and reworking the road base in the remainder of Stage 1 to keep roads driveable
- Excavation work near the Millpark Channel
- Installing new watermain along Millpark Street
Pump Station and Sewer Work
Work will also continue near the pump station area, including:
- Installing silt fencing for environmental protection
- Removing surface materials
- Installing new sanitary sewer infrastructure between the pump station and Union Road (the deepest sewer on the project)
What the Coloured Areas Mean on the Map
- Red areas: Roads will be ground and reworked to allow underground service installation while maintaining access for local traffic.
- Purple areas: Active excavation will be taking place. Expect heavier equipment and possible short-term delays.
- Blue area: A new watermain will be installed using directional drilling to minimize excavation and reduce disruptions.
![]()
Local access will be maintained wherever possible. Thank you for your patience as this important infrastructure work continues.
Share January 6, 2026 - Update on Facebook
Share January 6, 2026 - Update on Twitter
Share January 6, 2026 - Update on Linkedin
Email January 6, 2026 - Update link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends